Zu dieser Karteikarte gibt es einen kompletten Satz an Karteikarten. Kostenlos!
664
there will be a lot of changes in the conditions or work scope that impact
Just Click on Below Link To Download This Course:
https://www.devrycourses.com/product/devry-proj-410-quiz-2-latest/
(TCO 4) Human resources, procurement, real estate management, and accounting are examples of categories of business units that are typically _.
outsourced
contracted out to consultants
good examples of core company operations
best handled by internal employees
Instructor Explanation: Textbook pp. 2 – 3, Section 1.2 “What is BPO?”
Question 2. Question : (TCO 1) A fixed price or lump sum contract is best used when: __.
there will be a lot of changes in the conditions or work scope that impact the project outcome
there is no scope
https://www.devrycourses.com/product/devry-proj-410-quiz-2-latest/
(TCO 4) Human resources, procurement, real estate management, and accounting are examples of categories of business units that are typically _.
outsourced
contracted out to consultants
good examples of core company operations
best handled by internal employees
Instructor Explanation: Textbook pp. 2 – 3, Section 1.2 “What is BPO?”
Question 2. Question : (TCO 1) A fixed price or lump sum contract is best used when: __.
there will be a lot of changes in the conditions or work scope that impact the project outcome
there is no scope
Tags: DEVRY PROJ 410, DEVRY PROJ 410 QUIZ 2 LATEST
Quelle: https://www.devrycourses.com/product/devry-proj-410-quiz-2-latest/
Quelle: https://www.devrycourses.com/product/devry-proj-410-quiz-2-latest/
Karteninfo:
Autor: CoboCards-User
Oberthema: Education
Thema: Education
Schule / Uni: devry university
Ort: UK
Veröffentlicht: 12.02.2020