What are the earliest start and latest start for E?
Just Click on Below Link To Download This Course:
https://www.devrycourses.com/product/devry-gscm-530-week-5-homework-assignment-latest/
4.4.Answer the following questions for the following network.Times shown are in days.
.jpg”>
1.a.What is the length of the critical path?
2.b.What are the earliest start and latest start for E?
3.c.What is the latest start for B?
4.d.If all other tasks are completed in their expected durations, will the project length be affected if task B actually takes five days instead of the expected three?
5.6.Consider the following information about a small project:
https://www.devrycourses.com/product/devry-gscm-530-week-5-homework-assignment-latest/
4.4.Answer the following questions for the following network.Times shown are in days.
.jpg”>
1.a.What is the length of the critical path?
2.b.What are the earliest start and latest start for E?
3.c.What is the latest start for B?
4.d.If all other tasks are completed in their expected durations, will the project length be affected if task B actually takes five days instead of the expected three?
5.6.Consider the following information about a small project:
Tags: DEVRY GSCM 530 WEEK 5 HOMEWORK, DEVRY GSCM 530 WEEK 5 HOMEWORK ASSIGNMENT LATEST
Source: https://www.devrycourses.com/product/devry-gscm-530-week-5-homework-assignment-latest/
Source: https://www.devrycourses.com/product/devry-gscm-530-week-5-homework-assignment-latest/
Flashcard info:
Author: CoboCards-User
Main topic: Education
Topic: Education
School / Univ.: devry university
City: UK
Published: 12.02.2020